Price it before the labour walks off the job

The cheapest moment to price a variation is while the people who did it are on site and the plant is on hire. Once the trade has moved on and the finishes have gone over the work, the measure is buried and the cost a reconstruction. Get a number to every change within the month, even a provisional one: a figure built while the evidence is warm beats a perfect method on a cold memory.