It is the periodic measure of what the works are worth to date, produced by whoever is applying or certifying, and it is the number the whole payment cycle then runs on.
Measure against the priced document line by line, record the measure with its evidence as you take it, and reconcile the cumulative position each period so agreed lines stay agreed.
They record who and what was on site, where, and for how long, each day, which is the evidence behind daywork, disruption, delay and any argument about resourcing.
Design the capture around the people who will do it, give every record a named owner and a fixed moment, keep each one short, and check for gaps every month rather than at the end.
Whenever a contractual right depends on writing something down, or a fact will be worth proving later, and always in a flat factual register rather than an argumentative one.
Everything the contract requires in both directions: the insurances each party must hold, any performance bond, the collateral warranties owed, and the professional indemnity a designer carries.
The protection you were contractually promised simply is not there when you need it, and the loss it should have covered falls on you instead, usually discovered the day it is called on.
Long enough to outlast the period in which a claim can still be brought, which under a deed commonly runs many years past completion, so records are kept for the limitation tail, not until handover.