Explore all faqs for Variations in Quantity Surveying, with every available item in one place.
Every change, with its instruction reference, its status, its current value and its notice position, kept current enough to answer at a glance what is agreed, what is pending and what is at risk.
They still go into the application, at your honest current assessment marked as an assessment, because a variation left off until it is perfectly priced is a variation the other side gets to forget.
Both, at different moments: the site spots the change and flags it the day it happens, and the office confirms it in the contract's form and prices it, and the handover between them is where change gets lost.
You measure the instructed change against the contract's valuation rules, forecast quantities from the drawings, and price the parts you cannot rate yet as clearly provisional, with any time consequence flagged separately.
A signed sheet is worth far more, because a signature records agreement to the resources at the time, but an unsigned contemporaneous sheet still beats a reconstruction, so keep every sheet and chase the signatures.