Explore all faqs for Payments in Claims & Disputes, with every available item in one place.
The date the payment obligation crystallises for the cycle. Every other deadline counts from it.
Whenever the contract says, counted from the Due Date. Where the contract is silent, the Scheme's default is 17 days from the Due Date.
If the contract is for construction operations in Great Britain, usually yes. The main exception is work for a residential occupier.
On time, in the contract's form, stating the sum and basis clearly enough that it can stand as the Notified Sum by default.
The Payment Notice opens the cycle's response and sets the Notified Sum; the Pay Less Notice is the later, second chance to reduce it. Different windows, different reference dates.
Check the notice position first. Then the routes are a formal demand, statutory interest, suspension after proper notice, and adjudication.
Yes, if the Notified Sum is unpaid at the Final Date For Payment and you give at least 7 days' written notice first.
Generally not. The Construction Act outlaws them, with one narrow exception for upstream insolvency.
Yes. If the contract has no substantial interest remedy, statute implies 8% over base plus a fixed recovery sum.
The payer's statement of the sum it considers due, served within 5 days of the Due Date.
The payer, or a specified person the contract names. Authority matters; it is not just paperwork from anyone.
The sum considered due at the Due Date and the basis of calculation, shown line by line. Even a zero needs its arithmetic.
Inside the 5 day window, yes, a corrected notice can replace the first. After the window closes, no; the route is a Pay Less Notice.
There is no way to cure it. Once the 5 days pass, your remaining move is a Pay Less Notice.
The payee's application usually becomes the Notified Sum by default. The payer can still serve a Pay Less Notice; miss that too and the applied sum is payable in full.
The valuation can be negative, but the notice states zero as the sum due. Recovering the difference needs a contractual route or adjudication.
The payer's last chance to revise the sum payable, served before the prescribed period ahead of the Final Date For Payment.
A Payment Notice can reduce the application on its own. The Pay Less Notice is a separate second chance, not what a reducing Payment Notice turns into.
The payer, or a specified person the contract authorises. Never the payee.
Right sender, right window, sum plus basis of calculation, served the way the contract requires.
The sum considered due at the date of service and the basis of calculation, with every deduction itemised.
Confirm the deadline, build the calculation, state sum and basis, serve by the contract's method with proof.
In the window between the sum it answers existing and the prescribed period before the Final Date For Payment.
Whenever you intend to pay less than the current Notified Sum: disputed valuations, new set off, or a missed Payment Notice.
Until the prescribed period before the Final Date For Payment. Scheme default: 7 days. Check the contract.
Inside the window, a further notice can supersede the first. After the deadline, the served notice stands and nothing can be repaired.
It can, in principle, if the content is right and the contract's service rules allow it. The contract's notice clause decides.
Test its validity first: timing, content, sender, service. If it survives, dispute the valuation itself in adjudication.
Generally not from this cycle's Notified Sum. Deductions from the sum due need a valid Pay Less Notice served in time.
It can, if it satisfies both sets of rules, but relying on that is a gamble; serve each separately.
An adjudication enforcing the Notified Sum where the payer served no valid notice in time. It is decided on the notices, not the value of the work.
Attack the application's validity, look for a document that worked as a notice in substance, test service, and know the true value route if those fail.
An adjudication deciding what the work was actually worth, available to the payer only after the Notified Sum has been paid.