Claim the variations every month, priced or not
Leaving a variation out until it is perfectly priced poisons the account: months later the other side asks why work worth real money was never applied for. Put every variation in from the month it happens, at your honest current assessment, marked where the price still moves. The running claim is itself a record that the work was done and valued at the time.