When is the Final Date For Payment?
Whenever the contract says, counted from the Due Date. Where the contract is silent, the Scheme's default is 17 days from the Due Date.
Updated: 22 August 2026
The answer
The Final Date For Payment is the last day the money can lawfully arrive, and it is fixed by the contract as a period running from the Due Date, the date the payment obligation crystallises. The Construction Act lets the parties agree almost any period, so check the payment terms first: 14, 21, 28 and 35 days are all common, and heavily amended subcontracts sometimes stretch far longer. Where the contract does not provide an adequate mechanism, the Scheme for Construction Contracts, the statutory fallback, fills the gap with a default of 17 days from the Due Date. The date matters because other rights hang off it: the Pay Less Notice deadline counts back from it, 7 days under the Scheme, and the rights that follow non-payment, suspension after notice and statutory interest, only bite once it has passed with the Notified Sum unpaid. One more trap: the Act requires the period to run from the Due Date, so a term running it from delivery of an invoice rather than from the Due Date can fall foul of the Act and let the Scheme's timetable in.
The Scheme's defaults where the contract is silent
| Step | Scheme default |
|---|---|
| Due Date | The later of 7 days after the end of the payment period and the payee making its claim |
| Payment Notice | Within 5 days of the Due Date |
| Pay Less Notice | At least 7 days before the Final Date For Payment |
| Final Date For Payment | 17 days from the Due Date |
Example
Say a bricklayer's subcontract is silent on payment periods, so the Scheme steps in. The payment period ends on the 31st and the bricklayer applied on the 28th, so the Due Date is 7 days after the period ends. The payer then has 5 days from that Due Date to serve its Payment Notice, the Final Date For Payment falls 17 days after the Due Date, and any Pay Less Notice must land at least 7 days before that final date. Miss the arithmetic by a day at the last step and the deduction fails; pass the final date unpaid and suspension and interest rights open up. The lesson is that the whole timetable hangs off one date, so fix the Due Date first and diary the rest from it.
The free Notice & Deadline Register keeps every one of these dates in one place across your live jobs.